2025-01-27_SDGE_2025_Change Order Report_R0

P a g e | 1 San Diego Gas & Electric 2025 Change Order Request January 27, 2025 Electronic Filing OEIS Docket No. 2023-2025-WMP P a g e | 1 I. Change Order a. Introduction and Background The Office of Energy Infrastructure Safety’s (OEIS or Energy Safety) 2023-2025 Wildfire Mitigation Plan (WMP) Process Guid
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/28/2025 8:13:04 AM

Draft Decision for Liberty 2025 WMP Update

Draft Decision for Liberty 2025 WMP Update State of California – A Natural Resources Agency Gavin Newsom, Governor OFFICE OF ENERGY INFRASTRUCTURE SAFETY Caroline Thomas Jacobs, Director 715 P Street, 20th Floor | Sacramento, CA 95814 916.902.6000 | www.energysafety.ca.gov January 27, 2025 To: Stakeholders for the Liberty U
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Office of Energy Infrastructure Safety | Subjects Areas: | Date: 1/27/2025 1:59:06 PM

SCE 2023-2025 WMP Change Order

1 Connor J. Flanigan Managing Director, State Regulatory Operations connor.flanigan@sce.com Docket# 2023-2025-WMPs November 1, 2023 Lucy Morgans Program Manager, Electric Safety Policy Division Office of Energy Infrastructure Safety 715 P Street, 20th Floor Sacramento, CA 95814 SUBJECT: WMP 2024 Target Update Dear Program Manager Mor
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/24/2025 2:02:03 PM

2025.01.17_PC-23-07_Joint_IOU_CC_Workstream_2025 WMP Rpt

2025 WMP Update Joint IOU Covered Conductor Working Group Report Introduction: In the 2021 WMP Update Final Action Statements, Energy Safety ordered the Joint IOUs1 to coordinate to develop a consistent approach to evaluating the long-term risk reduction and cost-effectiveness of covered conductor (CC) deployment, including
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:17:50 PM

PC_2025_WMP Update_EFR Outage Summary 2023 Data Errata

EFR Outage Summary 2021 2022 2023 Number of Circuits with EFR tc={91488E89-C3FA-4E0B-9C45-B01545A81323}: [Threaded comment] Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924 [Tasks] There is a
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:17:34 PM

2025.01.17_PC_2025_WMP-Update_CA Line Rebuild Data 23-25

2023 - 2025 Plan State District Location (Circuit) Line Miles Planned Completion Year Status CA Yreka 5G40 1.16 2023 Complete CA Yreka 5G83 5.04 2023 Complete CA Mt Shasta 5G76/5G79 1.28 2023 Complete CA Mt Shasta 7G75 0.22 2023 Complete CA Yreka 5G83 1.71 2023 Complete CA Yreka 5G83 4.53 2023 Complete CA Yreka 5G83 2.09 2023 Complete CA Yreka 5G83 4.5
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:16:24 PM

2025.01.17_PC_2023-2025_Base_WMP_Revision_Rev 6 (R6) - Clean

Wildfire Mitigation Plan | Table of Contents 1 2023-2025 Wildfire Mitigation Plan R6 January 17, 2025 Wildfire Mitigation Plan | Table of Contents ii Wildfire Safety Page intentionally left blank Wildfire Mitigation Plan | Table of Contents iii Wildfire Safety Tab
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:14:51 PM

2025.01.17_PC_2023-2025_Base_WMP_Revision_Rev 6 (R6) - Redline

Wildfire Mitigation Plan | Table of Contents 1 2023-2025 Wildfire Mitigation Plan 2025 UpdateErrata Redline R5 R6 July 08August 19 September 20, 2024 January 17, 2025 Wildfire Mitigation Plan | Table of Contents ii Wildfire Safety Page intentionally left blank Wildfir
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:12:49 PM

2025.01.17_PC_2025_WMP_Update_Rev 2 (R2) Clean

Microsoft Word - 2025.01.17_PC_2025_WMP_Update_Clean Rev2.docx Wildfire Mitigation Plan | Updates to Risk Models 1 Wildfire Safety -08 2025 Wildfire Mitigation Plan Updates Rev 2 Standalone Document January 17, 2025 Wildfire Mitigation Plan | Updates to Risk Models 2 Wildfire Safety Table of Contents 1 Upda
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:10:34 PM

2025.01.17_PC_2025_WMP_Update_Rev 2 (R2) Redline

Wildfire Mitigation Plan | Updates to Risk Models 1 Wildfire Safety -08 2025 Wildfire Mitigation Plan Updates Rev 12 Standalone Document 07/08/2024September 20, 2024 January 17, 2025 Wildfire Mitigation Plan | Updates to Risk Models 2 Wildfire Safety Table of Contents 1 Updates to Risk Models ...........
Case: 2023-2025-WMPs | Document Type: | Submission Type: Document | Submitter Role: Utility | Subjects Areas: | Date: 1/17/2025 6:10:10 PM